Enjoying an inground pool on those hot summer days in Baltimore takes time, but our pool builders are experts at concrete pool construction! If you’ve been wondering about the process involved in building your dream pool, read on. 

At Elite Pools, we handle all the details of constructing a concrete pool. From the early planning stages and pool design to the final stages of opening a pool, we help customers with the entire process. 

What Services Are Available?

Elite Pools is available to create both residential and commercial pools in Baltimore, MD. We’ll help you figure out the best place in your backyard to install a pool, as well as the appropriate depth. If you’re looking to build a commercial pool in your community, we can help ensure it has the appropriate space for everyone’s needs.

Interested in water features for your inground pool, such as waterfalls? If you can dream it, we can design it. Let us know what you have in mind, and we’ll work with you to make it happen.

Are Renovations Available?

If an older pool no longer works for your family, we can update it. Reach out to us today to discuss your options for pool renovation. We’ll help transform your old pool into a dream pool that will serve you for years.

Building your pool

Step 1 – Pre-processing

All of the plans and legal documents are checked and verified. The pre-site and engineering equipment/products are ordered.

Step 2 – Permitting

Your permit is prepared and submitted to your county. The time this takes will vary depending on the city/county.

Step 3 – Virtual Reality Design

The crew will put all of your information into the computer and work on creating your own virtual reality oasis. This also allows for all of the information such as measurements/ last-minute design changes to be seen by the crew.

Step 4 – Final Processing

This is where all of the pre-grade is ordered and if there is anything that is already in the backyard would be removed to start renovating and digging.

Step 5 – Layout

On your property, Elite Pools will put a painted layout of exactly where your pool will go.

Step 6 – Excavation

This is where things might get dirty! The excavator arrives and digs up the dirt where your new pool will be.

Step 7 – Equipment and plumbing

Your pool equipment and plumbing will be installed at this point.

Step 8 – Steel

After Phase 7, steel rebar with spacers are installed to create the structure for your pool.

Step 9 – Electric

The electric wiring is then installed with all the necessary precautions.

Step 10 – Pre-gunite inspection

Before we can progress to the next stage, a city inspection is scheduled.

Step 11 – Shotcrete

Once the inspection is passed, concrete is installed to the pool’s interior.

Step 12 – Waterfall and boulders

If the pool owner wants, waterfalls and boulders would be added at this time.

Step 13 – DECKING AND PAVERS

At this time, decking and pavers can be installed.

Step 14 – Tile

Waterline tile is installed now.

Step 15 – Clean Up

The debris all in your backyard will be cleaned up and looking brand new with a new pool.

Step 16 – Fencing

Fencing will be put around your yard if desired.

Step 17 – Acrylic (if desired)

If your pool’s design is applicable, acrylic material will be added to the decking, allowing 24 hours to cure.

Step 18 – PRE-PLASTER INSPECTION

In order to ensure that all barrier requirements are completed, a city inspection needs to happen with you, the homeowner, to be present.

Step 19 – Interior finish

This is when the interior design is finally finished and we can start to fill your pool with water.

Step 20 – MECHANICAL START-UP

A start-up technician will then start up all of your equipment, they will also install a suction cleaner and add all of the necessary chemicals to help keep your pool perfect.

Step 21 – INTRODUCTION TO NEW POOL

This is when you are practically done with the pool building process!